02 · Project Scope & Objectives
Option
Project Scope

The project

The project is a flat-pack and fitted-furniture plant in Accra, Ghana, in a leased 800 m² factory at $4.20 per m² a month. The plant cuts and edges melamine board on CNC machines and sells through three routes: an online catalogue of flat-pack items, fitted projects (kitchens and closets, priced per m²), and, in the recommended plan, room packages for hotels and serviced apartments.

The owner funds the plant with equity only; there are no loans. Other private investors may join later through shares. The study covers five years from lease signing, in US dollars excluding VAT.

ItemSetting
LocationAccra, Ghana
Factory800 m² leased at $4.20 per m² a month ($3,360)
Rent36 months paid at signing ($120,960), accepted by the client
Set-up period3 months from lease signing to first production
Working patternOne shift: Monday–Friday 8 hours, Saturday 6 hours (about 199 machine hours a month)
FundingEquity only, no loans
Horizon and currency5 years from lease signing; USD, excluding VAT
TaxCorporate income tax 25%
Cost of capital21.07% a year (cost of equity, explained on the financial page)
Objectives

What the study is meant to decide

  • Decide whether the owner should commit equity to the plant, and on what conditions.
  • Set a price level the Accra market can accept, and test it against Kitea Ghana and local makers.
  • Size the equipment, staff and working capital for one shift, and find the bottleneck.
  • Show the funding need month by month, and the equity instalments that cover it.
  • Name the risks that decide the result, with red flags that tell the owner when to act.
Assumptions

What each option assumes

RuleBase (client prices)
PricesClient item cost × 1.6, unchanged (online catalogue average $199 an order; projects $205.7 per m²)
Project volume300 m² a month at full volume, as the client planned (price within 3% of the recommended plan's; the gap to the Accra guide is a risk both options share)
Online catalogue18.1 orders a month at the end of the ramp instead of the client's 20: fewer desks and shelves, which are priced 37–49% above Kitea
Project materials55% of the client's cost (our bill-of-materials check points higher)
Management and installationNot given by the client; our estimate added: management team $3,500 and one installation crew $1,200 a month
Insurance, vans, accounting; hidden-cost allowanceNot included (zero)
EquityTwo instalments: at signing and at production start

Caveats to read with this option

  • Prices built on the client's cost sit at 1.5–3 times Accra retail for catalogue items and about 33% above the Accra guide for projects.
  • The client's cost appears to spread labour and depreciation over very low output, or to count cutting twice. Any double counting inflates prices, not costs, in the model.
  • Against Kitea Ghana the client's storage items are close or cheaper, but the desks and the wall shelf are 37–49% dearer, so Base expects fewer of those orders.
  • Insurance, vans, accounting and a hidden-cost allowance are still not in the client's case.
RuleRecommended (Scenario 2 with improvements)
PricesHigher of production-module cost × 1.6 and the comparable Kitea Ghana price
LinesOnline catalogue, fitted projects, B2B room packages, installation as a separate fee
DeliveryPaid by the customer
Working patternOne shift
EquipmentAs listed by the client (CNC router included)
Cost baseFull: factory, installation and management salaries, utilities, insurance, marketing
EquityCommitment of $850,000 in three instalments

The four improvements (all on in this option)

ImprovementWhat it changes
L1Lean staffing: 11 operators and 14 helpers at full volume (manual stations are underused)
L2Order-book target between year 1 and year 2: an extra B2B contract signed in year 1 for delivery in year 2 (3 contracts in year 2 instead of 2)
L3Website running cost $150 a month instead of $500
L4Project customers pay a 50% deposit 30 days before installation (B2B deposit is already in the base case)

Each improvement is modest on its own. Together they lift the five-year NPV from ($93,671) to $17,197 and the IRR from 15.9% to 22.0%.

Start-up investment

What it takes to open

USDYear 0
Equipment and fit-out (machines duty-paid, installed)371,000
Rent paid in advance (36 months)120,960
Working capital (placeholder)60,000
Contingency39,260
Operating and pre-opening costs before production29,100
Total start-up investment620,320

Machines are taken as duty-paid and installed, as the client confirmed. Working capital is the client's placeholder. The monthly cash flow shows a peak need of $602,053; with the operating losses of the first months, equity paid in totals $641,313.

USDYear 0
Equipment and fit-out (depreciated)431,000
Permits, registration, fire and environmental8,000
Website and e-commerce build10,000
Feasibility study fee7,500
Rent paid in advance (36 months)120,960
Opening stock (working capital, year 0)37,625
Contingency (10% of equipment and fit-out)43,100
Total start-up investment658,185

Equipment and fit-out includes the client's list plus assembly benches, dust extraction and two installation vans. Opening stock follows the stock policy on the operations page. The equity needed ($718,405) is higher than this total because of the cash used before production pays its way.

Outside the scope

What the study does not cover

  • VAT: excluded from the study, as agreed.
  • Loans: dropped. A financial decision for later years, if needed.
  • A second shift: considered only once the bottleneck passes 85%.
  • Changes to the client's equipment list: the list stays as given.
  • Confirmed market data: no further client data is available, so project volume, project price and capacity remain stated assumptions. They are conditions for a final go.